2026 District Infrastructure Replacement Project Areas and Schedule
The 2026 DIRP projects are organized into four construction schedules: DIRP 2026 #1, DIRP 2026 #2, DIRP 2026 #3, and DIRP 2026 #4.
DIRP 2026 #2 was bid on February 4, 2026, and includes an optional scope expansion—via change order—to incorporate DIRP 2026 #4.
The bid tabulation for DIRP #2 is available here:
DIRP 2026 #1 was opened at 10:00 AM on February 27, 2026, at the District office.
DIRP #1 also includes a scope expansion, via change order, to incorporate DIRP 2026 #3.
2026 Construction Schedule
DIRP 2026 #1 Schedule
- Mobilization: May 18 – May 19, 2026 (S Union Blvd and W Jewell Ave)
- Asphalt Milling: May 19- May 22, 2026
- Waterline Installation: May 20- May 29, 2026
- Project Completion (DIRP #1): August 2026
DIRP 2026 #2 Schedule
- Mobilization: March 31 – April 4, 2026
- Asphalt Milling: April 6
- Waterline Installation: April 6 – April 10, 2026 (S Braun St) Completed
- Waterline Installation: April 22- End of May, 2026 (S Arbutus St from W Alkire to S Beech Dr)
- Project Completion (DIRP #2): 08/05/2026
DIRP 2026 #3 – Draft Schedule
- District, Lakewood, Denver Water Reviews: 04/06/2026 – 06/29/2026
- Change Order into DIRP #1: 08/24/2026
- Project Completion (DIRP #3): 11/20/2026
DIRP 2026 #4 – Draft Schedule
- District, Lakewood, Denver Water Reviews: 04/06/2026 – 06/29/2026
- Change Order into DIRP #2: 08/05/2026
- Project Completion (DIRP #4): 11/03/2026